epeleg Posted November 29, 2011 Report Share Posted November 29, 2011 on plasticscm 4, When setting up sync replication between two servers, do I need to set up: Server2 as source and Server1 as target in addition to setting up Server1 as source and Server2 as target ? Link to comment Share on other sites More sharing options...
manu Posted November 30, 2011 Report Share Posted November 30, 2011 Hi epeleg, You just need to create a new "Sync view", then add a new source repository and finally add a target repository. You will see the incoming and outgoing changes between the two repositories. That's all you need to have them synchronized. Regards, manu Link to comment Share on other sites More sharing options...
psantosl Posted December 3, 2011 Report Share Posted December 3, 2011 http://codicesoftware.blogspot.com/2011/08/this-is-how-i-use-synch-view.html Link to comment Share on other sites More sharing options...
epeleg Posted December 6, 2011 Author Report Share Posted December 6, 2011 I understand that the only meaning for the source and target are just a way to define the meaning of push and pull. i.e. a push is from the source to the target and a pull is from the target to the source Thanks. Link to comment Share on other sites More sharing options...
manu Posted December 7, 2011 Report Share Posted December 7, 2011 Yep! that's the idea! Link to comment Share on other sites More sharing options...